Patio Concrete Calculator

Estimate the concrete your patio layout will take—from a simple rectangle or circle to an L-shaped patio, curved half-circle, or measured custom area. See cubic yards, whole bags, and a rounded ready-mix order with a live plan drawing.

6 footprint modesUS & metricNo login required

Interactive concrete estimator

How much concrete do you need for your patio?

Choose a footprint, enter the dimensions inside your forms, and let the calculator handle volume, whole-bag rounding and ready-mix increments.

Live estimate
Concrete including allowance2.61 yd³118 × 80 lb bags at selected example yield
Try a layout:

1. Patio footprint

Select the shape that fits the concrete area—not the landscaping boundary outside the forms.

Example only—use the depth required by your actual project.
Added after the measured concrete volume.
2. Openings, second pad & thickened sectionsOptional · avoid double-counting

The extra-depth area must lie inside the combined concrete footprint. The second pad must not overlap the main area. The diagram is a quantity aid, not a survey or engineered plan.

3. Bags, supplier rounding & optional pricesChange product yields and quotations
Set to 0 to disable order rounding; check local delivery minimums.

Prices are entered by you, not live quotes. They exclude excavation, forming, reinforcement, labor, tax, pumps and finishing unless separately included in your price.

Concrete including 10% allowance2.61 yd³Rounded for display, before supplier purchasing increment
Ready-mix order (example increment)2.75 yd³
80 lb bags (example yield)118 bags
Net patio concrete volume2.37 yd³
Net plan area192.0 ft²
Your patio footprintRectangle · 16 × 12 ft
Live SVG
Patio layout and dimensionsIllustrative overhead patio shape, updated as dimensions change. Optional secondary pad is drawn separately, not positioned at surveyed coordinates.
Illustrative plan, not to scale for attachments or openings. Use measured, non-overlapping dimensions.
How many bags?Click a size to use it as your selected bag
Per-bag material estimateEnter a bag price
Ready-mix material & delivery estimateEnter a supplier quote

A 16 × 12 ft patio at 4 in thick contains 64.00 ft³ of concrete. With 10% allowance: 70.40 ft³.

See the step-by-step quantity breakdown
Calculated concrete takeoff
ComponentAreaVolume
Main footprint192.0 ft²2.37 yd³
Net192.0 ft²2.37 yd³
Allowance10%0.24 yd³
Order basisBefore supplier rounding2.61 yd³

Material takeoff, not structural design. Thickness, reinforcement, base, joints, drainage, footing details and product mix must be selected for your real project. An SVG export is an illustrative estimate, not a construction drawing.

Quick answer: To estimate patio concrete, calculate the area inside the forms, multiply by planned thickness and convert to cubic yards: area (ft²) × thickness (in) ÷ 324. For a 16 × 12 ft patio at 4 inches: 2.37 yd³ net. With an illustrative 10% allowance, estimate 2.61 yd³ before delivery rounding.

Accurate layouts, fewer surprises

Choose the correct patio shape

Most mistakes start with measuring the wrong area. Select a plan shape that represents the concrete inside the forms. For irregular spaces, divide the footprint into non-overlapping parts, or measure the actual area and choose Custom measured area.

Rectangle or square

Measure length and width perpendicular to each other. Great for most simple patios and pads.

Round or half-round

Use the full diameter. A half-circle is exactly half the area of a full circle at the same diameter.

L-shaped patio

Outer length × outer width minus the missing corner. No manually overlapping rectangles.

Right triangle

Enter the two perpendicular legs, not a diagonal side. The area is half a rectangle.

How to measure an L shape: measure the full outside rectangle, then measure the empty inside-corner rectangle and subtract it. For a 20 × 16 ft outer footprint with an 8 × 6 ft missing corner, concrete area is 272 ft², not 320 ft² and not 368 ft².
Simple math, correctly applied

Patio concrete formulas

Rectangular slab (US units)yd³ = area in ft² × thickness in inches ÷ 324For metric: m³ = area (m²) × thickness (mm) ÷ 1,000.
Area formulas used by the calculator
ShapeAreaKey measurement
RectangleLength × widthTwo perpendicular sides
Circleπ × diameter² ÷ 4Full diameter through center
Half-circleπ × diameter² ÷ 8Full straight-edge diameter
Right triangleLeg 1 × leg 2 ÷ 2Perpendicular sides
L shapeOuter L × outer W − notch L × notch WActual missing inside corner
Custom areaMeasured or previously calculated areaVerified non-overlapping footprint

Openings: deduct the area that does not receive concrete. Additional pad: add its full independent volume only when it does not overlap the main patio. Thickened region: multiply its area by the extra depth only, because the base slab thickness is already counted.

Realistic quantity references

How many cubic yards of concrete for common patio sizes?

The table gives net geometric volume for a uniform rectangular patio, before any allowance or order rounding. Thicknesses are arithmetic examples, not recommendations for specific soils, loads or local code.

Concrete required, in cubic yards, by patio dimensions and thickness
Patio sizeArea4 in5 in6 in
10 × 10 ft100 ft²1.231.541.85
12 × 12 ft144 ft²1.782.222.67
16 × 12 ft192 ft²2.372.963.56
20 × 20 ft400 ft²4.946.177.41

Example A: 16 × 12 ft rectangular patio

  1. Area = 16 × 12 = 192 ft².
  2. Net = 192 × 4 ÷ 324 = 2.37 yd³.
  3. With 10% extra = 2.61 yd³.
  4. At 0.25 yd³ ordering increments = 2.75 yd³.
  5. At 0.60 ft³ per 80-lb bag = 118 bags.

Example B: 20 × 16 ft L-shaped patio

  1. Outer rectangle = 20 × 16 = 320 ft².
  2. Inside corner cutout = 8 × 6 = 48 ft².
  3. Actual patio area = 272 ft².
  4. At 4 in: net volume = 3.36 yd³.
  5. With 10% extra = 3.69 yd³ before supplier rounding.
What the estimate cannot see

Before ordering concrete: six patio checks

01

Check elevations and drainage

Confirm finished patio height at doors, siding, steps and adjoining grade. Identify where surface runoff will go before setting forms. The calculator multiplies measured placed thickness; it does not design drainage.

02

Account for actual excavation

Measure grade and form depth after preparation. Over-digging, variable ground, missing corners and low spots can create extra volume. The allowance does not replace field measurement.

03

Keep base material separate

Concrete volume is not crushed-stone base volume. The optional gravel result reports compacted in-place geometry only; ask your aggregate supplier about loose volume, compaction and density before buying.

04

Plan joints before placement

Contraction joints should define usable panels rather than leaving one unbroken L-shaped panel. NRMCA CIP 6 discusses spacing, near-square panels and isolation at adjacent structures. See the joint guide.

05

Plan a suitable outdoor finish

A patio may need a slip-resistant broom texture, decorative finish or another approved surface. Finishing changes tools, labor and timing—even if the volume stays the same. See concrete patio planning.

06

Schedule curing and traffic control

Have protection materials on site before placing concrete. Curing is not simply waiting for the surface to look dry. Use the mix and project guidance for access and future sealing. See curing methods.

Patio area and concrete thickness are different measurements

Measure the horizontal footprint inside the forms for area. Measure from the prepared supporting surface to the finished concrete level for thickness. A gravel layer belongs in a separate quantity.

The required layer thickness, drainage slope, reinforcement and site details depend on your application and applicable requirements—not the calculator preset.

Ordering and purchasing

Bags or ready-mix for a concrete patio?

Bagged concrete

Compare the actual bag’s finished yield and your mixing capacity. A 16 × 12 ft patio at 4 inches with 10% extra needs 118 bags of 80-lb mix at 0.60 ft³/bag—9,440 lb of dry bags to store, handle, mix and transport.

Smaller bag counts do not automatically mean less labor; continuous placement matters. Check water, mixing and placement instructions for the product.

Compare concrete bag yields →

Ready-mixed concrete

Give your supplier the required concrete performance, calculated quantity, site access, unloading method, placement schedule and any local delivery constraints. The tool’s quarter-yard rounding is editable and is not a supplier minimum.

For the same example, the estimate is 2.61 yd³ with allowance, or 2.75 yd³ at an illustrative 0.25 yd³ increment.

Build the full project budget →

Do not use a generic calculator result to approve a hot-tub pad, masonry fireplace, patio roof columns or other concentrated loads. Such elements may need separately designed concrete supports and quantities.

Questions homeowners and installers ask

Patio concrete calculator FAQs

How much concrete do I need for a 12 × 12 patio?

A 12 × 12 ft patio has 144 ft² of area. At a purely illustrative 4 in thickness, its net concrete volume is 144 × 4 ÷ 324 = 1.78 yd³. A 10% allowance increases the estimate to 1.96 yd³ before any ready-mix increment. Verify the project’s required thickness and actual grade.

How many yards of concrete for a 20 × 20 patio?

At 4 in thick, a 20 × 20 ft patio contains 400 × 4 ÷ 324 = 4.94 yd³ net. With 10% extra it is about 5.43 yd³, before supplier rounding. The result rises if the chosen thickness, additional sections or local low spots increase actual placed volume.

How do I calculate an L-shaped patio without double-counting the corner?

Select L-shaped and enter the full outside length and width, then the length and width of the empty inside corner. The calculator subtracts the notch once. Only use the optional separate pad for a genuinely non-overlapping piece outside that L-shaped footprint.

Does the calculator support a round patio or semicircle?

Yes. Enter the full diameter in round or half-round mode. The round area is π × diameter² ÷ 4; the half-round area is π × diameter² ÷ 8. Use the custom measured-area mode for an irregular freeform curve or a circular segment that is not exactly a semicircle.

Can I enter different concrete thicknesses?

Yes. The optional separate rectangular pad accepts its own thickness. For an approved thickened region within the patio, use its area and additional depth, rather than counting its full depth again. Neither feature selects a structurally safe thickness.

Can I subtract a planter bed or firepit opening?

Yes. Select the opening option and enter its measured area in square feet or square meters. The opening must be inside the main shape and must not overlap another deduction. Its volume is deducted at the main patio thickness.

Is the gravel base included in the concrete cubic yards?

No. The gravel-base option is a separate compacted geometric volume. It is not added to concrete volume and does not estimate tons, loose aggregate delivery or compaction factors. Use the planned base depth and supplier information.

How many 80 lb bags equal one cubic yard?

At QUIKRETE Concrete Mix No. 1101’s approximate yield of 0.60 ft³ per 80-lb bag, 27 ÷ 0.60 = 45 bags per cubic yard, before extra allowance. Other concrete mix products have different yields. Select Custom to enter your actual package yield.

Does it calculate ready-mix cost?

It can compare optional bagged material cost with supplier-quoted ready-mix material and delivery charges, using the rounded order quantity. It does not retrieve live local prices, and estimates exclude labor, base prep, reinforcement and finishing unless those are explicitly reflected in your quote.

How thick should my concrete patio be?

Thickness depends on loading, supporting ground, exposure, edge details and applicable requirements. The preset 4-inch value demonstrates volume math; it is not approval for every patio, accessory, vehicle or soil condition. Review the slab-thickness guide and the required project details.

What about slope, joints and curing?

These are independent construction decisions. Establish a suitable drainage and elevation plan, joint layout and curing method with the project requirements before pouring. Visit the patio project center, control-joint guide and curing guide.

Sources and technical references

Formulas are geometric volume calculations. Example bag yields and construction guidance are grounded in the following publications; follow the actual product data, drawings and applicable local requirements.