6 footings in example1.09 yd³ with 10% extra49 bags at 0.60 ft³/bag
Quick answer: For a pier with a separate bottom pad, calculate the concrete-filled shaft above the pad plus the pad volume. Multiply by the number of footings and add your chosen allowance. Concrete quantity does not establish the required footing diameter, soil bearing capacity, frost depth or reinforcement.

Live concrete estimator

How much concrete for your deck footings?

Start with dimensions from your permitted plan or an approved footing detail. Watch the cross-section change with the footing type.

Updates as you type
1

Footing shape & dimensions

This is a cylindrical disk at the bottom, not a flared bell. Its volume is counted separately from the shaft.

2

Bags & ordering

Fine-tune yield, ready-mix increments & prices

Prices are optional, user-entered material rates only. Delivery, mixing labor, pump charges, tax and site work are not automatically included.

Concrete with 10% allowance

Whole 80-lb bags (combined order)49 bags
Ready-mix required1.09 yd³

A quarter-yard supplier increment rounds the ready-mix order to 1.25 yd³.

Net concrete0.99 yd³
Per footing (net)4.45 ft³
Bottom pad total12.57 ft³
Separate-pour bags54 bags
Rounded ready-mix order1.25 yd³
Dry weight of purchased bags3,920 lb

Dry bag weight is a handling estimate, not a truck, trailer or lifting capacity. Combined pour: 49 bags. If each pier is separately rounded to whole bags, plan 54 bags. Actual purchasing depends on how pours are staged.

Deck concrete footing cross-sectionSchematic of an above-grade post base, round concrete shaft and optional spread footing. Dimensions update with the calculator; not drawn to scale. Finished grade (schematic) 36 in shaft height Ø 12 in Ø 24 in bottom pad 8 in pad
Illustrative section: the separate pad is below the shaft. Do not include the pad thickness in the shaft height. Dimensions are not a construction specification.

Compare bag sizes

40 lb980.30 ft³/bag
50 lb790.375 ft³/bag
60 lb660.45 ft³/bag
80 lb490.60 ft³/bag

Example finished yields from QUIKRETE Concrete Mix No. 1101. Other products may differ.

Material-only price comparison

Bagged concreteEnter a bag price
Ready-mix concreteEnter a yd³ price

Not an installed-price comparison. Account for delivery, minimum-load charges, equipment, labor and access.

This tool estimates concrete materials from dimensions you enter. It does not design a safe deck, footing, post anchor or soil foundation. Check the approved detail and local requirements before excavating or ordering.

What size deck footings do you need?

Concrete volume and required footing size are different questions. The volume tool above assumes the diameters and thicknesses are already selected. Footing sizing depends on the tributary deck load carried by each post, verified soil bearing, deck geometry, frost protection, anchorage and applicable code. The same deck can require different footings at end posts and interior posts.

Before choosing a diameter

  1. Determine which joists and beams transfer load to each post.
  2. Use the applicable local deck tables or a qualified design to establish post reactions.
  3. Confirm allowable soil bearing—not just surface soil appearance.
  4. Check required footing plan size, thickness, embedment, frost protection and anchor detail.
Schematic deck tributary load area flowing to beam supportsIllustrative tributary stripLoads transfer through the beam to each post
Tributary area is the portion of deck load attributed to a support, not necessarily the full deck area divided evenly among all posts.

How many deck footings will you need?

There is no universal footing count or spacing for a 12 × 12, 12 × 16, or 16 × 20 deck. Post locations follow the framing plan, beam spans and overhangs, joist direction, ledger or freestanding support, loads and the approved connection details. An end support and an interior support may not carry the same tributary area. Use your permitted framing layout to count footings; the concrete calculator then multiplies each matching footing group.

Optional arithmetic worksheet · not structural design

Understand bearing-area math

Explore the relationship between an already-determined support load and soil bearing. This simplifies the problem to vertical bearing only and does not select or approve a footing size.

Illustrative vertical load2,000 lb
Bearing area (load ÷ soil value)1.33 ft²
Equivalent round contact diameter15.6 in

Do not use the 15.6-inch arithmetic result as a footing design. It omits footing self-weight, moment, lateral/uplift forces, settlement, eccentricity, frost, footing thickness, reinforcement and minimum prescribed sizes. Actual tables can require larger footings.

Reference example from an established deck guide

AWC's DCA 6 (2015 IRC–based edition), Table B3, uses a defined deck-load basis and reports illustrative round-footing sizes for known tributary areas and soil assumptions. For example, its 40 ft² / 1,500 psf entry specifies a 16-inch round footing, a 15 × 15-inch square alternative, and 6-inch footing thickness under that table's stated conditions. It is a historical prescriptive example—not an automatic approval under your jurisdiction's currently adopted code.

See the 2024 IRC foundation provisions and your locally adopted deck-footing requirements. Do not apply an exemption for a low, freestanding deck to an attached or elevated deck without confirming eligibility.

Deck footing concrete formulas (with diagrams)

Measure all dimensions inside the form in a consistent unit. The three modes calculate non-overlapping shapes; choose the shape that actually matches the planned pour.

Straight cylindrical pierØ D

Straight pier

>V = π × (D ÷ 2)² × H, where D and H are in feet. This is one round concrete-filled shaft.

Round shaft on wider circular bottom padshaftround pad

Shaft + round pad

V = πrs²H + πrp²T. H is shaft height above the pad; T is the pad thickness.

Round shaft on wider rectangular bottom padshaftL × W × T

Shaft + rectangular pad

V = πrs²H + L × W × T. The footing block must not overlap the shaft volume.

Conversions: divide cubic feet by 27 to get cubic yards; multiply cubic yards by 0.764554858 for m³. Add allowance before dividing by the chosen finished bag yield. For an accurate bag order, round up to whole bags after calculating the required volume.

Worked example: six deck piers with bottom footings

The original page's example is retained because it demonstrates the most important measurement convention. Assume a concrete shaft 12 inches in inside diameter and 36 inches tall above a separate 24-inch-diameter by 8-inch-thick round pad. Those are illustrative dimensions, not recommendations for a deck.

Six-footing concrete takeoff before and after a 10% allowance
ItemPer footingSix footings
12-in shaft × 36-in height2.356 ft³14.137 ft³
24-in round pad × 8-in thick2.094 ft³12.566 ft³
Net concrete4.451 ft³26.704 ft³ (0.989 yd³)
With 10% additional concrete4.896 ft³29.374 ft³ (1.088 yd³)
80-lb bags at 0.60 ft³ yield9 if rounded separately49 pooled; 54 separately rounded
Common overcount: If the overall filled concrete depth is 44 inches and the pad is 8 inches thick, the shaft height entered here is 36 inches. Entering 44 inches for the shaft and adding the pad counts the central overlap twice.

How many bags per deck footing?

These examples use a straight 36-inch-tall cylinder only, without an added spread pad, waste or supplier rounding. The selected concrete product determines the actual yield; use its data sheet rather than assuming every bag of the same weight is equivalent.

Illustrative bags for one 36-inch-tall straight pier using QUIKRETE Concrete Mix No. 1101 yields
Shaft diameterNet concrete60-lb bags (0.45 ft³)80-lb bags (0.60 ft³)
8 in1.05 ft³3 bags2 bags
10 in1.64 ft³4 bags3 bags
12 in2.36 ft³6 bags4 bags
16 in4.19 ft³10 bags7 bags
18 in5.30 ft³12 bags9 bags

For a project with multiple footings, add any separate pad volumes, multiply by quantity, apply the desired allowance, and calculate the whole-bag count. Use the Sonotube Calculator for a simpler straight round-form estimate, or the Concrete Bag Calculator for other shapes and yields.

How deep should deck footings go?

The required footing depth is controlled by the locally adopted building code, frost exposure, site conditions and the approved design. Depth to the bottom of the footing is not necessarily the same as the height of concrete in a Sonotube. Excavation may include a pad, gravel layer (only when specified), or other structural details.

AWC DCA 6 explains that its prescriptive footings bear on undisturbed soil at least 12 inches below the undisturbed ground surface or below the applicable frost line, whichever is deeper, subject to the adopted code. There are jurisdiction-specific exceptions and alternate approved systems, so do not use a national frost-depth guess.

Footings near the house foundation, those in fill, and those supporting concentrated loads deserve extra attention. Before digging, locate buried utilities (in the U.S., contact 811) and confirm any inspection required before the pour.

Illustrative deck pier with footing below an indicated frost depthGradeLocal frost line (illustrative)Depth tobearing base
Section is explanatory only. The diagram does not establish the required frost depth or an approved foundation detail.

Deck footing planning checklist: before you pour

Use this list when comparing contractor quotes or preparing for a permitted deck footing inspection. Check boxes are stored only in your browser.

Pre-pour review

0 of 8 complete
01

Confirm the detail

Get the footing dimensions and local approval before using material quantities to place an order.

02

Measure every group

Group identical piers. Calculate deeper or differently shaped footings separately.

03

Plan the pour

Compare available mixer capacity and working time with a ready-mix delivery. Confirm access and minimum loads.

04

Protect and document

Follow mixture, inspection, post-anchor and curing requirements. Keep product data and pour records.

Five deck-footing estimating mistakes to avoid

  1. Using a guessed footing diameter. The concrete estimator never checks soil, structural loads or local footing tables.
  2. Counting the pad twice. The entered shaft height must stop at the top of a separate bottom pad.
  3. Confusing excavation depth with concrete-filled height. A hole depth may include non-concrete layers or a footing detail not captured by a tube measurement.
  4. Ignoring varying ground elevations. On sloped lots, a shared top elevation can produce different shaft lengths. Take off distinct groups.
  5. Treating bag weights as yields. Bag count must use the specific product's installed volume; dry bag weight is not wet concrete volume.

Deck footing calculator FAQs

How many bags of concrete do I need for deck footings?

Calculate each footing's concrete volume from the shaft and any separate bottom pad, multiply by the number of footings and add the desired material allowance. Divide that total by the bag's labeled finished yield, then round up. In the example here, six 12-inch shafts on 24-inch round pads require 49 bags at a 0.60 ft³ yield with 10% extra.

What size footings do I need for a 12 × 16 deck?

Deck plan dimensions alone are not enough to size footings. The number of beams and posts, their tributary areas, span/overhang arrangement, loads, actual soil bearing and frost requirements matter. Use the adopted deck tables or an approved design before entering dimensions into the material calculator.

How many footings do I need for a 12 × 12 or 12 × 16 deck?

The plan area by itself cannot determine the number. Beam spans, joist spans, number of support lines, ledgers versus freestanding frames, overhangs and design loads control footing count and placement. Follow a permitted framing plan or an appropriate prescriptive design; then enter the actual number of identical footings into the quantity calculator.

How deep should a deck footing be?

Follow local code, frost-protection rules and the approved foundation detail. The depth to the footing's bearing surface is different from the amount of concrete in the shaft if a bottom spread pad or other layers are present. Ask the authority having jurisdiction about local requirements.

Does a 12-inch Sonotube need a wider footing at the bottom?

Not always, but the tube diameter alone does not establish sufficient soil-bearing area. Some approved details use a wider round or square spread footing and others use engineered alternatives. Confirm the appropriate footing system for the design, then calculate the volumes without overlap.

How do I calculate a square deck footing under a round pier?

Select “Round shaft + rectangular bottom pad.” Enter the pad length, width and thickness separately from the round shaft's diameter and height above the pad. The tool adds the rectangular prism and cylindrical shaft volumes. It does not check footing bending or capacity.

Can I use the estimated soil-bearing diameter to build my deck?

No. The worksheet only divides an assumed vertical load by an assumed soil bearing pressure and converts area to an equivalent circle. It does not address required design details, footing self-weight, minimums, settlement, frost, uplift, lateral loads or structural capacity. Use a locally accepted design.

How many 80-lb bags fill a 12-inch-diameter, 3-foot-tall round pier?

A straight cylinder of that size contains about 2.356 ft³. At the example yield of 0.60 ft³ per 80-lb bag, it takes four whole bags without extra allowance; five if a 10% allowance is applied and each pier is rounded separately. Product yields vary.

Why does the calculator show two bag counts?

A pooled count rounds once after combining all concrete. A separate-pour count rounds each footing's volume up to whole bags before multiplying by the number of footings. The latter can be higher when the pours are staged and leftover mixed concrete cannot be shared.

Can I use a flared or proprietary deck-footing base?

Not with the generic flat pad geometry unless it accurately matches the product. A tapered bell or proprietary base requires its actual dimensions or published concrete capacity. Obtain the manufacturer's form volume and the approved design detail.

Can I pour deck footings with ready-mix instead of bags?

Yes, if the specified concrete and delivery plan are suitable. Use the volume with allowance, then apply your supplier's agreed order increment. Confirm any minimum delivery, short-load charges, access, unloading time, placement equipment and inspection schedule.

Technical references and methods

Sources are linked so you can verify product yields, prescriptive examples and code terminology. Requirements vary by jurisdiction and adopted edition.

Scroll to Top