Concrete estimating tools

Concrete Slab Calculator

Estimate how much concrete a slab needs in cubic yards or cubic meters. Add a four-sided thickened edge, compare bag sizes, and plan your ready-mix order.

Cubic yards & m³40–80 lb bagsThickened edgesUS & metric

LIVE SLAB ESTIMATE

How much concrete do you need?

Edit dimensions; results update automatically.

Ready-mix order 3.50 yd³80 lb bag option 147 bags
Quick sizes (ft):
Enter the thickness specified for your project.
For different sizes, estimate separately.
Thickness:
2. Edge detail and orderingOptional features
An inward band below the regular slab.
Editable estimating allowance; not a required standard.
Bag size, measurement units, order increments & costs
Switching converts existing values.
Read the exact product label; yields vary.
0 = no increment rounding. Confirm with supplier.
Illustrative estimate, not a lifting or structural rating.
Material-only; excludes delivery.
Cost uses whole bags, before tax.

Ready-mix order · with allowance and rounding

3.50 yd³

3.26 yd³ needed with 10% extra, rounded upward to a 0.25 yd³ increment.

Net slab volume2.96 yd³
Concrete with extra3.26 yd³
Selected whole bags147 × 80 lb
Slab plan area240 ft²
Approx. wet concrete with allowance: 13,200 lbSelected bag option: 11,760 lb of dry bags
Visualize your slab
Slab dimensions and thickened-edge diagramTop plan and cross-section diagrams show length, width, slab thickness, and any perimeter band. The illustration is schematic. 20 ft length12 ft widthUniform slabPlan geometry · diagram is illustrative
The slab is uniform. Turn on four-sided thickening to see its added material.

Material takeoff, not a structural design. Verify field measurements, specified slab detail, mixture, and delivery minimums.

Compare bag sizes

Selected: 80 lb

Approximate yields for QUIKRETE Concrete Mix No. 1101; verify the product label. Counts include your allowance but not truck-order increment rounding.

Concrete slab formula: cubic yards = length (ft) × width (ft) × thickness (in) ÷ 324. For a 20 × 12 ft slab at 4 inches thick, the net volume is 2.96 yd³. With 10% additional material, the estimate is 3.26 yd³; a supplier using ¼-yard increments would round the order up to 3.50 yd³.

On this page
  1. How to measure a slab
  2. Concrete slab formulas
  3. How thickened edges work
  4. Worked 20 × 12 ft example
  5. Slab thickness and volume chart
  6. Bags vs. ready-mix: what to order
  7. Before you pour
  8. Frequently asked questions
  9. Sources

How to measure concrete for a slab

Measure the outside length and width of the finished concrete inside the formwork, then enter the planned concrete thickness—not the combined thickness of concrete and gravel base. The calculator converts those measurements into cubic feet, cubic yards or cubic meters and applies the allowance you choose. If the slab is deeper in some locations, use measured depth zones rather than relying on one edge measurement.

01

Measure length and width

Use the full rectangular pour area. Record any cutouts or separate shapes independently.

02

Measure concrete thickness

Check excavation and compacted base elevations before the concrete truck arrives.

03

Add edge details and an allowance

Model a four-sided inward perimeter thickening only when the project actually has one.

04

Confirm order and delivery

Ask the producer about minimums, increments, access, concrete mixture, and timing.

For L-shaped or irregular slabs, divide the area into non-overlapping rectangles, estimate each one and combine their net concrete before applying a single allowance. An opening or void should be deducted only when it truly does not receive concrete. Separate pours may need their own bag or truck rounding.

Concrete slab formulas: cubic yards, cubic feet and bags

US customaryyd³ = L(ft) × W(ft) × T(in) ÷ 324

Because 12 inches make a foot and 27 cubic feet make a cubic yard.

Metricm³ = L(m) × W(m) × T(mm) ÷ 1,000

Convert the slab thickness from millimeters to meters.

Whole bagsBags = ⌈ft³ with allowance ÷ ft³ per bag⌉

Always round up to whole packages; verify the label yield.

For n identical slabs, multiply one slab’s net concrete by n before adding the allowance and choosing the supplier increment. The calculator rounds the combined total as one order. If deliveries or batches are separate, calculate their purchase quantities independently.

Thickened-edge concrete slab calculation

A perimeter-thickened slab has a regular slab thickness plus additional depth along an inward band. The calculator's edge option covers all four sides and avoids adding concrete twice at the corners. The depth entry is the concrete below the regular slab, not the total edge depth.

Four-sided slab band planA larger rectangle with an inner rectangle removed shows a continuous band around the four slab edges. Corners belong to the ring once.Inner slab areaOutside length (L)Width (W)Band width bFour-sided band: corners counted once
Plan view: the shaded ring is outside area minus inside area.
Thickened-edge concrete slab sectionA thin slab spans between thickened edges. Dimension arrows show regular thickness and additional depth below it.T = regular thicknessd = extra depthb = band widthSection is not a design detail
Cross-section: add only the extra depth below the regular slab.
Band area = L × W − (L − 2b) × (W − 2b)Extra edge concrete = band area × d. Total net volume = (L × W × t) + (band area × d). Use consistent length units before calculating.

Example: A 20 × 12 ft slab with a 12 in (1 ft) inward band has 240 − (18 × 10) = 60 ft² of thickened-edge area. If that band extends 8 in below the normal slab thickness, it adds 60 × 8/12 = 40 ft³, or approximately 1.48 yd³. The four corner squares are counted once, not twice.

This formula does not cover a beam along one side, sloped haunches, separate footings, interior thickenings, openings or post-tensioned foundation design. Those features need separate takeoffs from the approved drawings.

Worked example: 20 × 12 ft concrete slab

4 in slab, 10% allowance, ¼-yard ordering increment; example only
QuantityUniform slab12 in band + 8 in extra edge depth
Surface area240 ft²240 ft²
Main slab volume80 ft³80 ft³
Additional edge0 ft³40 ft³
Net concrete volume2.96 yd³4.44 yd³
With 10% extra3.26 yd³4.89 yd³
Supplier increment rounded3.50 yd³5.00 yd³
80 lb bags at 0.60 ft³ yield147 bags220 bags

The net concrete is geometric volume; the allowance is additional planned material; the final rounded quantity is a possible purchase quantity. These figures are deliberately separate so you can see exactly where additional cubic yards enter the estimate.

Concrete slab thickness and cubic yard chart

The following chart shows how much concrete 100 ft² of uniform slab takes before additional material. It demonstrates the volume change when thickness changes; it is not a recommendation for a particular vehicle, building, soil or load.

100 ft² of concrete slab, no thickened edge and no allowance
Concrete thicknessCubic feetCubic yards80 lb bags, approx.
3 in25.000.9342
4 in33.331.2356
5 in41.671.5470
6 in50.001.8584
8 in66.672.47112

Increasing a 20 × 12 ft slab from 4 in to 5 in adds 20 ft³, or approximately 0.74 yd³ before extra allowance. Check the specified slab thickness independently; our slab thickness guide covers the factors that govern the design.

How many bags or how many yards of ready-mix?

Bagged premixed concrete and ready-mix are two alternative ways to supply the same geometric slab volume. Do not apply ready-mix truck rounding to the bag estimate. The bag count is based on finished concrete yield per whole bag; ready-mix is ordered by volume and may be subject to producer-specific increments or minimums.

Example yields from QUIKRETE Concrete Mix No. 1101
Bag sizeExample finished yieldWhole bags for 1 yd³, no extraWhole bags for 20 × 12 × 4 in slab, 10% extra
40 lb0.30 ft³90294
50 lb0.375 ft³72235
60 lb0.45 ft³60196
80 lb0.60 ft³45147

These are manufacturer-specific approximate yields, not values that every premixed product must meet. The example would require 147 bags weighing 80 lb each—11,760 lb of packaged dry material before mixing water. A large whole-bag count can be expensive to transport and labor-intensive to mix and place. Compare the full cost of mixing and placement with a ready-mix quote, including delivery and short-load fees.

NRMCA's CIP 31 guide to ordering ready-mixed concrete emphasizes communicating project requirements and the intended use to the supplier. The calculator does not determine a concrete mix design, truck access, delivery time or supplier minimum order.

Concrete slab order and pre-pour checklist

Use this checklist before placing an order. Checkmarks are saved in your browser when storage is available.

Pre-pour readiness0 of 7 complete

Even a precise volume calculation cannot prove foundation adequacy, load capacity, reinforcing requirements or local-code compliance. Design information should come from the responsible professional and applicable project documents; ACI's concrete floor and slab construction guide discusses preparation, joints, finishing and curing.

Frequently asked questions

How many cubic yards do I need for a 10 × 10 slab at 4 inches?

A 10 × 10 ft slab at 4 in is 100 × 4 ÷ 324 = 1.2346 yd³, or about 1.23 yd³ net. With a 10% allowance it needs about 1.36 yd³; if the producer accepts quarter-yard increments the result rounds up to 1.50 yd³.

How much concrete is in a 20 × 20 slab at 4 inches?

400 ft² × 4/12 ft = 133.33 ft³, which is 4.94 yd³ net. Adding 10% gives approximately 5.43 yd³. A supplier using 0.25 yd³ order increments would round that up to 5.50 yd³.

How many 80 lb bags make one cubic yard of concrete?

If the specific product yields 0.60 ft³ per 80 lb bag, 27 ÷ 0.60 = 45 bags make one cubic yard before any allowance. Other concrete products can have different yields, so use the actual label.

Does the calculator include thickened slab edges?

Yes. Select “Yes — all four sides” and enter the inward band width plus the additional depth below the regular slab. Its ring-area formula counts each corner once. It does not estimate single-sided or tapered edges automatically.

Is extra edge depth the same as total edge depth?

No. If the main slab is 4 in thick and the total edge depth is 12 in, the additional depth is 8 in. Entering 12 in as extra depth would count the regular slab thickness twice along the edge.

Can I estimate two slabs at once?

Yes, when both slabs have exactly the same dimensions and edge detail. Set the identical-slab count to 2. For different slab dimensions or separate pour dates, calculate them separately and make a combined purchase plan.

Should I order exactly the calculated net volume?

The net result assumes ideal dimensions with no variation or loss. Confirm field measurements, apply an allowance appropriate to your project, and discuss actual truck-order increments and minimum loads with the producer.

Does a 4-inch slab work for driveways, garages and buildings?

This calculator cannot determine a safe thickness. Loads, ground support, reinforcement, exposure and project specifications can require different details. The 4-inch starting value is a calculation example, not a design recommendation.

How does switching from US to metric change my estimate?

It converts the numerical dimensions to meters and millimeters so the physical slab stays the same. Output volumes are shown in cubic meters instead of cubic yards. Switching units is not the same as changing a 20 ft dimension to 20 m.

Sources and technical references

The formulas are geometric calculations. The sources below support product yields, ordering practices and slab construction considerations; they do not substitute for a project specification.

Scroll to Top