Concrete estimating tools · Free online calculator
Concrete Calculator: Cubic Yards, Bags & Ready-Mix
Measure a slab, footing, round hole, or set of solid steps. See the concrete you need in cubic yards, compare whole bags, and get a rounded ready-mix order—with your own allowance.
Calculate your concrete
Choose what you're pouring, then enter the actual inside dimensions.
3.26 yd³ with 10% extra, rounded up in 0.25 yd³ increments.
Optional material price comparison
Illustrative totals from your inputs, not a contractor's installed price. Tax, labor, short-load and placement costs are excluded unless built into a rate.
See full results, units & bag-size comparison
Default example estimate. Results update when JavaScript is available.
This estimate represents a substantial number of heavy bags. Compare delivery, mixing capacity, and placement labor with a ready-mix quote.
For jobs with more than one shape
Combine several pours into one order
Calculate one section above and select Add this pour to project. Repeat for a slab, footing, or post holes. The project total applies your chosen allowance once to the combined net volumes, then rounds a single ready-mix order. Individual sections can be removed.
| Section | Net volume | Remove |
|---|
For separate delivery dates, estimate and round each order separately. Project totals do not automatically include thickened edges, displaced posts, undercuts, or other geometry not entered.
On this page: formulas, examples & ordering advice
How to use this concrete calculator
Choose the concrete shape
Use Slab for rectangular flatwork; Footing for a continuous rectangular strip; Round hole for a filled cylindrical form; or Steps for a completely solid stair profile.
Enter dimensions in the units shown
In US mode, plan dimensions use feet while thickness, footing width, depths, and hole diameter use inches. Metric mode uses meters for plan dimensions and millimeters for smaller dimensions. Enter actual formed measurements, not the area of gravel below concrete.
Choose quantity, allowance, and a bag yield
Quantity multiplies identical sections. The allowance is applied to total measured concrete; the truck increment then rounds the ready-mix order upward. Bag counts are independently rounded to whole bags at your selected product yield.
To solve backward from a fixed amount of concrete, choose Slab → Calculate → Missing length, width, or thickness. The calculator removes the extra allowance from your available quantity before finding the missing dimension; it does not recommend structurally safe dimensions.
Which shape matches your concrete project?
Slabs, patios & driveways
Length × width × thickness. Measure the concrete thickness, not excavation depth. Add different edge thickenings as separate non-overlapping volumes.
Continuous footings
Run length × concrete width × filled depth. For varying widths or grades, divide the footing into separate sections.
Round piers & holes
π × (inside radius)² × concrete-filled depth. This is gross hole volume; embedded posts or voids may displace concrete.
Solid concrete stairs
Models each full tread block as taller than the previous one. It does not model hollow steps, footings beneath stairs, or an overlapping top landing.
These are quantity calculations, not structural designs. Slab thickness, reinforcing, frost depth, compressive strength, stairs, accessibility, and other requirements must come from the applicable project design and local code.
Concrete volume formulas and unit conversions
A cubic yard contains 27 cubic feet. Use consistent units before multiplying. The formulas below show the shape volumes before adding allowance or supplier rounding.
| Use case | Formula |
|---|---|
| Slab (feet, inches) | Length (ft) × width (ft) × thickness (in) ÷ 324 = yd³ |
| Rectangular footing | Length (ft) × width (in) × depth (in) ÷ 3,888 = yd³ |
| Round filled hole | π × [diameter (in) ÷ 2]² × depth (in) ÷ 46,656 = yd³ |
| Solid, full-depth stairs | Width × rise × run × n(n + 1) ÷ 2, using feet for every dimension; ÷ 27 for yd³ |
| Concrete with allowance | Net yd³ × (1 + allowance % ÷ 100) |
| Bags to purchase | Round up [concrete required (ft³) ÷ bag yield (ft³)] |
| Metric slab | Length (m) × width (m) × thickness (mm) ÷ 1,000 = m³ |
Conversions: 1 yd³ = 27 ft³ ≈ 0.7646 m³; 1 m³ ≈ 1.308 yd³. In US slab formulas, dividing by 324 combines 12 inches per foot and 27 cubic feet per cubic yard.
For a variable-thickness pour, calculate each thickness zone separately. For posts, subtract only the actual volume displaced within the filled hole. Do not subtract the post twice.
Worked example: a 20 × 12 ft slab, 4 inches thick
Step 1 — Net concrete: 20 × 12 × 4 ÷ 324 = 2.963 yd³ (80 ft³).
Step 2 — With 10% extra: 2.963 × 1.10 = 3.259 yd³ (88 ft³).
Step 3 — Ready-mix order: Round 3.259 upward to the next 0.25 yd³ = 3.50 yd³.
Step 4 — Bags instead: 88 ÷ 0.60 ft³ per 80 lb bag = 146.67, or 147 whole bags.
Ready-mix rounding and bag rounding are different purchasing decisions. Do not use the 3.50 yd³ truck-rounded amount to calculate bag counts—the bagged option uses the unrounded required volume (88 ft³). Confirm actual supplier increments and minimum order size before purchasing.
How many square feet does a cubic yard cover?
At uniform thickness, one cubic yard covers the areas below before any allowance. These are mathematical coverages—not recommended slab thicknesses.
| Thickness | Area covered | Example context |
|---|---|---|
| 3 in | 108 ft² | Only where the specified design permits |
| 4 in | 81 ft² | Common nominal thickness in small flatwork examples |
| 5 in | 64.8 ft² | Thicker flatwork examples |
| 6 in | 54 ft² | Higher-volume flatwork examples |
| Slab size | Net cubic yards | 80 lb bags* |
|---|---|---|
| 10 × 10 ft | 1.23 yd³ | 56 bags |
| 10 × 20 ft | 2.47 yd³ | 112 bags |
| 12 × 12 ft | 1.78 yd³ | 80 bags |
| 20 × 20 ft | 4.94 yd³ | 223 bags |
*Example bag counts use 0.60 ft³ finished yield per bag and always round up. They do not include extra allowance; the interactive calculator can apply your chosen percentage.
How many bags of concrete are in a cubic yard?
The answer depends on the finished yield per bag, not just the package weight. These values are from the QUIKRETE Concrete Mix No. 1101 product data sheet and should not be assumed for every concrete product.
| Bag weight | Approx. finished yield | Whole bags / yd³ |
|---|---|---|
| 40 lb | 0.30 ft³ | 90 |
| 50 lb | 0.375 ft³ | 72 |
| 60 lb | 0.45 ft³ | 60 |
| 80 lb | 0.60 ft³ | 45 |
| 90 lb (regional) | 0.675 ft³ | 40 |
Specialty bag mixes, repair mortars, grouts, and lightweight concrete may yield different volumes. In the calculator, choose Custom yield and enter the manufacturer’s stated finished yield under Advanced options. As bag quantities increase, include mixing capacity, crew time, lifting, and delivery access in your decision.
Before you order ready-mix or purchase bags
Use this quick check so a correct volume calculation translates into a workable pour. Your checklist progress is stored only in this browser when local storage is available.
See the National Ready Mixed Concrete Association’s Concrete in Practice library for technical resources, including CIP 8 (yield discrepancies) and CIP 31 (ordering ready-mixed concrete).
Frequently asked questions
How do I calculate how many yards of concrete I need?
Multiply length × width × thickness, with every dimension expressed in feet, to obtain cubic feet. Divide by 27 for cubic yards. If thickness is entered in inches, multiply length (ft) × width (ft) × thickness (in) and divide by 324. Add your chosen allowance afterward.
How many 80 lb bags of concrete make 1 cubic yard?
At 0.60 ft³ of finished yield per bag, 27 ÷ 0.60 = 45 bags before allowance. With 10% extra, 29.7 ÷ 0.60 = 49.5, so round up to 50 whole bags. Check the yield of your specific product.
How much concrete do I need for a 10 × 10 slab at 4 inches thick?
The geometric volume is 10 × 10 × 4 ÷ 324 = 1.235 yd³. With 10% extra, that becomes approximately 1.358 yd³. If the supplier sells in 0.25 yd³ increments, the rounded ready-mix order would be 1.50 yd³.
Should I add 5% or 10% extra concrete?
There is no universal allowance. Some jobs use a planning margin of approximately 5%–10%, but irregular excavation, changing thickness, form movement, and uncertain measurements can require a different approach. Measure known additional volumes explicitly and ask your supplier or contractor what allowance is appropriate.
Why does the ready-mix order exceed the calculated cubic yards?
The calculator first adds the extra allowance and then rounds upward to the truck-order increment you enter. For example, 3.259 yd³ becomes 3.50 yd³ in quarter-yard increments. Your supplier may also impose a separate minimum load or short-load fee.
How do I calculate multiple slabs or different shapes together?
Use the quantity field for identical sections. For different shapes or dimensions, calculate each one and select Add this pour to project. The project planner combines the measured volumes before applying one common allowance and ready-mix rounding rule. Estimate separate deliveries independently.
Can I solve for slab thickness from a known amount of concrete?
Yes. In Slab mode, change Calculate to Missing thickness, enter the volume available including allowance, and provide slab length and width. The result is geometric only. Do not alter a required structural thickness to fit an existing order without the responsible designer’s approval.
Can I use the same calculator for fence posts or hollow stairs?
Round-hole mode calculates the full cylindrical hole, so embedded posts displace some concrete. Stairs mode assumes full solid tread blocks and does not subtract voids or include a separate landing. For these conditions, calculate the actual net geometry or use a more specialized estimating tool.
Sources & calculation assumptions
Dimensional formulas are geometric. Example bag yields come from product-specific manufacturer information. Supplier and project requirements take precedence over planning defaults.
- QUIKRETE Concrete Mix No. 1101 technical data — stated finished yields for 40, 50, 60, 80, and 90 lb bags.
- NRMCA Concrete in Practice index — CIP 8, Discrepancies in Yield; CIP 31, Ordering Ready Mixed Concrete.
Calculator assumptions: rectangular uniform-volume sections; cylinders filled to the entered depth; stairs modeled as solid stair blocks; standard volumetric unit conversions; illustrative density; a user-selected allowance; and user-controlled rounding increments. No current concrete prices or supplier-specific minimums are assumed.